MAGNESIUM ELEKTRON LIMITED
Company number: 03141950
Reporting period:
1 July 2024 to 31 December 2024
Report filed on:
30 January 2025
Approved by:
Stephen Webster
Payment statistics
Late and disputed:
- payments due in the reporting period which have not been paid within the agreed period: 43%
Payment terms
Shortest standard payment periods
30 days
Longest standard payment period
120 days
Standard payment terms
Majority of our suppliers are on 30 days, we do start by offering 60 days however most suppliers tend to enforce 30 days
Were there any changes to the standard payment terms in the reporting period?
No
Were suppliers notified or consulted about these changes before they were made?
N/A
Maximum contractual payment period agreed
120 days
N/A
Any other information about payment terms
N/A
Dispute resolution process
Invoice queries are dealt with in a timely manner, to ensure invoices are paid on time. Any disputes are raised by either procurement and/or the Purchase requisitioner. Once this has been resolved, AP will deal with the invoice based on what was agreed. AP Specialist reaches out to supplier upon delayed receipt of the vendor invoice. It is typical that there is a delay in receiving the invoices, which allows for extended due dates. Purchasing department will also discuss any issues directly with the vendors regarding errors within the order upon receipt of the incorrect goods or upon receipt of the erroneous invoice.
Other payment information
Has this business signed up to a code of conduct or standards on payment practices? If so, which?
For example, signatories to The Fair Payment Code must commit to paying 95% of their invoices within 60 days.
No, this business has not signed up to a code of conduct or standards on payment practices.
Does this business offer e-invoicing in relation to qualifying contracts?
This is where suppliers can electronically submit and track invoices. It's not just allowing suppliers to email them an invoice.
Yes
Does this business offer supply chain finance?
This is where a supplier who has submitted an invoice can be paid by a third-party finance provider earlier than the agreed payment date. The business would then pay the finance provider the invoiced sum.
No
Under its payment practices and policies, can this business deduct sums from payments under qualifying contracts as a charge for remaining on a supplier list?
No
During the reporting period, did the business deduct sums from payments as a charge for remaining on a supplier list?
No