Published reports

NEO ENERGY PETROLEUM LIMITED

Company number: 03288689

This information is as reported by the business, and responses are in their own words.

Reporting period:

1 January 2023 to 30 June 2023

Report filed on:

20 July 2023

Approved by:

Robert Gair


Payment statistics

Average time taken to pay invoices: 18 days

Invoices paid:

  • within 30 days: 100%

Late and disputed:

Payment terms

Shortest standard payment periods

10 days

Longest standard payment period

45 days

Standard payment terms

Our standard payment terms are 30 days from the receipt of a valid invoice to our accounts payable email inbox.

Were there any changes to the standard payment terms in the reporting period?

No

Were suppliers notified or consulted about these changes before they were made?

N/A

Maximum contractual payment period agreed

45 days

No further comment provided

Any other information about payment terms

No further comment provided

Dispute resolution process

NEO Energy seeks to advise suppliers promptly of any disputes or reasons why an invoice will not be paid in accordance with the agreed terms. Once resolved, payment is made in accordance with the terms of the contract/PO. NEO Energy provides a centralised point of contact for suppliers' enquiries via its dedicated email Inbox where the team supports any questions related to, but not limited to, payment due dates, incorrect invoice submission, wrong or missing PO detail etc.

Other payment information

Has this business signed up to a code of conduct or standards on payment practices? If so, which?

For example, signatories to The Fair Payment Code must commit to paying 95% of their invoices within 60 days.

No, this business has not signed up to a code of conduct or standards on payment practices.

Does this business offer e-invoicing in relation to qualifying contracts?

This is where suppliers can electronically submit and track invoices. It's not just allowing suppliers to email them an invoice.

No

Does this business offer supply chain finance?

This is where a supplier who has submitted an invoice can be paid by a third-party finance provider earlier than the agreed payment date. The business would then pay the finance provider the invoiced sum.

No

Under its payment practices and policies, can this business deduct sums from payments under qualifying contracts as a charge for remaining on a supplier list?

No

During the reporting period, did the business deduct sums from payments as a charge for remaining on a supplier list?

No