BETA This is a new service – your feedback will help us to improve it.

HENRY BOOT DEVELOPMENTS LIMITED

Company number: 01390361

Reporting period:
1 July 2022 to 31 December 2022


Warning This information is as reported by the business, and responses are in their own words.

This report was filed on 27 January 2023

and approved by Darren Littlewood

Payment statistics

Average time taken to pay invoices: 33 days

Invoices paid:

Invoices due but not paid within agreed terms: 50 %

Payment terms

Shortest standard payment period

14 days

Longest standard payment period

30 days

Standard payment terms

Henry Boot Developments standard supplier payment terms are between 14 - 30 days from date of invoice. This is subject terms contained within a specific contract.

Due date is calculated by applying agreed terms to the invoice date. If an invoice falls due during a weekend or bank holiday, the payment transaction is executed on the following business day.

All invoices received are required to comply with our invoice requirements, otherwise we reserve the right to not process the document for payment until it has been corrected. Terms are negotiated and agreed with suppliers on initial engagement.

Were there any changes to the standard payment terms in the reporting period?

No

Maximum contractual payment period agreed

30 days

Any other information about payment terms

N/A

Dispute resolution process

In the event of a complaint or dispute about the payment of an invoice, in the first instance contact should be made with the relevant company’s purchase ledger department to find out what the problem is. If the Purchase Ledger contact is unable to tell you the details of the dispute on your invoice, in the second instance, contact should be made with the person who placed the order with the relevant supplier.

In respect of suppliers of goods, goods received are inspected and receipted on site with any issues arising communicated to the supplier via telephone or email.

For construction related payments and disputes, this is governed by the relevant sub-contract, which complies with the UK Construction Act and may contain more specific procedures or requirements.

Other payment information

Has this business signed up to a code of conduct or standards on payment practices? If so, which?

For example, signatories to The Prompt Payment Code must commit to paying 95% of their invoices within 60 days.

No

Does this business offer e-invoicing in relation to qualifying contracts? This is where suppliers can electronically submit and track invoices. It’s not just allowing suppliers to email them an invoice.

No

Does this business offer supply chain finance? This is where a supplier who has submitted an invoice can be paid by a third-party finance provider earlier than the agreed payment date. The business would then pay the finance provider the invoiced sum.

No

Under its payment practices and policies, can this business deduct sums from payments under qualifying contracts as a charge for remaining on a supplier list?

No

During the reporting period, did the business deduct sums from payments as a charge for remaining on a supplier list?

No