Company number: 03311781
and approved by James Wimpenny
Average time taken to pay invoices: 45 days
Invoices paid:
Invoices due but not paid within agreed terms: 49%
30 days
60 days
Payment terms are agreed with sub-contractors and suppliers as part of contract negotiations and to comply with any statutory and contractual requirements. The most frequently used payment terms in the reporting period for contracts relating to the supply of goods and services are 30 days and for contracts for the supply of goods only 60 days.
Answer not provided
N/A
60 days
N/A
N/A
BAM Construct UK Limited proactively seeks to avoid disputes by discussing any disagreements or issues with the relevant sub-contractor or supplier and, in particular, it has regular dialogue with its key supply chain partners at senior management level. Where it is not possible to reach agreement on any dispute there are a number of potential dispute resolution methods available to the parties including mediation, adjudication, expert determination and litigation.
For example, signatories to The Prompt Payment Code must commit to paying 95% of their invoices within 60 days.
Yes, this business has signed up to: Prompt Payment Code
This is where suppliers can electronically submit and track invoices. It's not just allowing suppliers to email them an invoice.
No
This is where a supplier who has submitted an invoice can be paid by a third-party finance provider earlier than the agreed payment date. The business would then pay the finance provider the invoiced sum.
No
No
No