Payment statistics

Average time taken to pay invoices: 52 days

Invoices paid:

Invoices due but not paid within agreed terms: 35 %

Payment terms

Shortest standard payment period

7 days

Longest standard payment period

90 days

Standard payment terms

The company operates two distinct payment processes:
1. Purchase Order (Mainly materials and plant)
Payment terms are agreed with suppliers on a case by case basis. The most commonly used terms are 30 days following the end of the month in which the tax point of the suppliers’ invoice falls.
The maximum agreed payment term is 60 days.

2. Sub contract Orders
There are two main types of sub contractor
1. Agency Labour
Standard payment terms vary between 7 days and 60 days from the end of the month in which the tax point of the invoice falls.
The maximum agreed payment term is 90 days.

2. Supply & Fix

Standard payment terms and conditions with sub contractors are in staged payments. Due dates for these staged payments are agreed at the outset of each contract being placed.
The average payment periods fall between 30 and 60 days following the certification of applications for payment or invoices received from the sub contractor.
The maximum agreed payment term is 60 days.

Were there any changes to the standard payment terms in the reporting period?

No

Maximum contractual payment period agreed

90 days

Any other information about payment terms

N/A

Dispute resolution process

Purchase Orders
Queries regarding materials and equipment hire are dealt with by the procurement team for resolution through dialogue with the supplier.
Sub contractor Orders
Queries regarding Sub contractor orders are dealt with by the surveyor responsible for the contract with the aim of reaching a resolution within the payment terms. If the dispute cannot be resolved, it is referred to the Supply Chain Director.

Other payment information

Has this business signed up to a code of conduct or standards on payment practices? If so, which?

For example, signatories to The Prompt Payment Code must commit to paying 95% of their invoices within 60 days.

No

Does this business offer e-invoicing in relation to qualifying contracts? This is where suppliers can electronically submit and track invoices. It’s not just allowing suppliers to email them an invoice.

No

Does this business offer supply chain finance? This is where a supplier who has submitted an invoice can be paid by a third-party finance provider earlier than the agreed payment date. The business would then pay the finance provider the invoiced sum.

No

Under its payment practices and policies, can this business deduct sums from payments under qualifying contracts as a charge for remaining on a supplier list?

No

During the reporting period, did the business deduct sums from payments as a charge for remaining on a supplier list?

No