Contracts and payments
Do any of this business's construction contracts with its suppliers include retention clauses? No
Payment statistics
Average time taken to pay invoices: 51 days
Total value paid:
- within 30 days: £6,168,184 (16%)
- in 31 to 60 days: £25,546,846 (67%)
- in 61 days or more: £6,289,799 (17%)
Invoices paid:
- within 30 days: 17%
- in 31 to 60 days: 67%
- in 61 days or more: 16%
Late and disputed:
- total value of payments due in the reporting period which have not been paid within the agreed period: £33,595,920
- payments due in the reporting period which have not been paid within the agreed period: 88%
- not made in the reporting period due to a dispute: 0%
Payment terms
Shortest standard payment periods
30 days
Longest standard payment period
90 days
Standard payment terms
The standard payment term for most suppliers in the UK is the first working day of the second month following date of invoice (for example, invoices dated between 1st and 31st of January would be paid on the 1st March). As an exception some UK utilities, local authority and small professional services may be paid within 30 days of the invoice date.
Overseas suppliers are paid within the first 5 days of the second month following the receipt of the goods.
Were there any changes to the standard payment terms in the reporting period?
No
Were suppliers notified or consulted about these changes before they were made?
N/A
Maximum contractual payment period agreed
100 days
No further comment provided
Any other information about payment terms
No further comment provided
Dispute resolution process
We have a dedicated accounts payable department that is contactable by phone (01909 476101 - option 4) and email (accounts.payable@pandrol.com)
Other payment information
Has this business signed up to a code of conduct or standards on payment practices? If so, which?
For example, signatories to The Fair Payment Code must commit to paying 95% of their invoices within 60 days.
No, this business has not signed up to a code of conduct or standards on payment practices.
Does this business offer e-invoicing in relation to qualifying contracts?
This is where suppliers can electronically submit and track invoices. It's not just allowing suppliers to email them an invoice.
No
Does this business offer supply chain finance?
This is where a supplier who has submitted an invoice can be paid by a third-party finance provider earlier than the agreed payment date. The business would then pay the finance provider the invoiced sum.
No
Under its payment practices and policies, can this business deduct sums from payments under qualifying contracts as a charge for remaining on a supplier list?
No
During the reporting period, did the business deduct sums from payments as a charge for remaining on a supplier list?
No