ASTRAZENECA UK LIMITED
Company number: 03674842
Reporting period:
1 January 2026 to 30 June 2026
Report filed on:
3 August 2026
Approved by:
Mani Sharma
Contracts and payments
Do any of this business's construction contracts with its suppliers include retention clauses? Yes
Payment statistics
Average time taken to pay invoices: 49 days
Total value paid:
- within 30 days: £1,075,897,231 (37%)
- in 31 to 60 days: £1,286,721,603 (44%)
- in 61 days or more: £574,584,260 (20%)
Invoices paid:
- within 30 days: 39%
- in 31 to 60 days: 57%
- in 61 days or more: 4%
Late and disputed:
- total value of payments due in the reporting period which have not been paid within the agreed period: £129,217,398
- payments due in the reporting period which have not been paid within the agreed period: 2%
- not made in the reporting period due to a dispute: 0%
Payment terms
Shortest standard payment periods
0 days
Longest standard payment period
120 days
Standard payment terms
Standard terms range from immediate payment to 120 days.
Were there any changes to the standard payment terms in the reporting period?
No
Were suppliers notified or consulted about these changes before they were made?
N/A
Maximum contractual payment period agreed
120 days
No further comment provided
Any other information about payment terms
No further comment provided
Retention clauses
How does this business use retention clauses?
Retention clauses are used in specific circumstances:
Retention rights are included in relevant Master Agreements and generally flow down into related SOWs or project contracts.
Does this business only use retention clauses in construction contracts above a specific contract sum?
No
Does this business use a standard percentage rate in retention clauses?
No
Does this business apply retention clause practices that are no more onerous than those applied to it on the same project?
Yes:
Our policy is to apply retention rights through relevant Master Agreements, with those rights generally flowing down into related SOWs or project contracts where applicable.
Releasing money under a retention clause
Process for releasing money this business has deducted or retained under a retention clause
Money retained under a retention clause is released in accordance with the relevant contract terms.
Is the money released in stages?
No
Amount retained from suppliers in the reporting period
Amount retained stated as a percentage of the money retained from this business by its clients
0%
Amount retained stated as a percentage of the total construction payments made by this business
0%
Dispute resolution process
Invoices are matched on receipt and disputed invoices notified to the supplier. Disputes are managed directly with the supplier and resolved items are reprocessed. Disputes are resolved within the existing payment terms.
Other payment information
Has this business signed up to a code of conduct or standards on payment practices? If so, which?
For example, signatories to The Fair Payment Code must commit to paying 95% of their invoices within 60 days.
Yes, this business has signed up to: Fair Payment Code
Does this business offer e-invoicing in relation to qualifying contracts?
This is where suppliers can electronically submit and track invoices. It's not just allowing suppliers to email them an invoice.
Yes
Does this business offer supply chain finance?
This is where a supplier who has submitted an invoice can be paid by a third-party finance provider earlier than the agreed payment date. The business would then pay the finance provider the invoiced sum.
Yes
Under its payment practices and policies, can this business deduct sums from payments under qualifying contracts as a charge for remaining on a supplier list?
No
During the reporting period, did the business deduct sums from payments as a charge for remaining on a supplier list?
No