B W INTERIORS LIMITED

Company number: 04018003

This information is as reported by the business, and responses are in their own words.

Reporting period:

1 January 2026 to 30 June 2026

Report filed on:

30 July 2026

Approved by:

Andrew Bradley


Contracts and payments

Do any of this business's construction contracts with its suppliers include retention clauses? Yes

Payment statistics

Average time taken to pay invoices: 29 days

Total value paid:

  • within 30 days: £71,257,234  (56%)
  • in 31 to 60 days: £51,802,222  (41%)
  • in 61 days or more: £4,633,754  (4%)

Invoices paid:

  • within 30 days: 55%
  • in 31 to 60 days: 41%
  • in 61 days or more: 4%

Late and disputed:

  • total value of payments due in the reporting period which have not been paid within the agreed period: £4,672,254
  • payments due in the reporting period which have not been paid within the agreed period: 3%
  • not made in the reporting period due to a dispute: 1%

Payment terms

Shortest standard payment periods

14 days

Longest standard payment period

60 days

Standard payment terms

Payment terms are adjusted to align with the clients payment terms. All subcontractors are consulted in advance

Were there any changes to the standard payment terms in the reporting period?

No

Were suppliers notified or consulted about these changes before they were made?

N/A

Maximum contractual payment period agreed

60 days

No further comment provided

Any other information about payment terms

No further comment provided

Retention clauses

How does this business use retention clauses?

Retention clauses are used in specific circumstances:

Our standard contracts do contain retention clauses, however, we operate a preferred subcontractor scheme which reduces it along with temporary works, scaffolding and other contracts which would not normally have retention applied to them.

Does this business only use retention clauses in construction contracts above a specific contract sum?

No

Does this business use a standard percentage rate in retention clauses?

Yes: 5%

Does this business apply retention clause practices that are no more onerous than those applied to it on the same project?

Yes:

Retention is only applied to certain contractors and we operate a preferred subcontractor scheme which reduces it. This ensures our retention clauses are no more onerous than our clients.

Releasing money under a retention clause

Process for releasing money this business has deducted or retained under a retention clause

If retention is held against a subcontractor, 50% is released on the certified completion of the works (or a specific date in the sub-contract). The balance is then released by the specified dates in accordance with the Housing Grants, Construction and Regeneration Act 1996.

Is the money released in stages?

Yes:

Completion of the works (or a specific date in the sub-contract). The balance is then released by the specified dates in accordance with the Housing Grants, Construction and Regeneration Act 1996.

Amount retained from suppliers in the reporting period

Amount retained stated as a percentage of the money retained from this business by its clients

72%

Amount retained stated as a percentage of the total construction payments made by this business

2%

Dispute resolution process

Details for our dispute resolution process are contained within our subcontractor orders. Initial disputes are handled by the relevant Commercial Director and then on to the Financial Director. BW aim to resolve all disputes as quickly as possible.

Other payment information

Has this business signed up to a code of conduct or standards on payment practices? If so, which?

For example, signatories to The Fair Payment Code must commit to paying 95% of their invoices within 60 days.

No, this business has not signed up to a code of conduct or standards on payment practices.

Does this business offer e-invoicing in relation to qualifying contracts?

This is where suppliers can electronically submit and track invoices. It's not just allowing suppliers to email them an invoice.

No

Does this business offer supply chain finance?

This is where a supplier who has submitted an invoice can be paid by a third-party finance provider earlier than the agreed payment date. The business would then pay the finance provider the invoiced sum.

No

Under its payment practices and policies, can this business deduct sums from payments under qualifying contracts as a charge for remaining on a supplier list?

No

During the reporting period, did the business deduct sums from payments as a charge for remaining on a supplier list?

No